AWARDED TENDER LIST AWARDED BY KRIDE
SL NOTENDER  NOTICE  No.Tender invite DateTender  Award DateNAME OF WORK AWARDED VALUE IN Rs.CONTRACTOR
1KRIDE/ADMIN/09/OFFICE INTERIORS/201930.12.201929.01.2020Office Interiors for KRIDE office at 1st Floor, Samparka Soudha Opp to Orion Mall Rajajingar, Bangalore28081271.6M/s. BUCON Engineers & Infrastrcuture Pvt Ltd, Mumbai
2KRIDE/Projects/60/202028.10.202014.05.2021 Improved Switch Expansion Joints for 60 Kg & 52 Kg Rails.19186812M/s. Ganpati Industrial Pvt Ltd
Kolkata
3KRIDE/Projects/37/LS/202020.02.202018.05.2020Cadastral Land Survey, Collection of Land Documents, Identification, Ownership Verification, foint Measurement, Preparation of Land Acquisition plans and Associated Works in connection with the work of Bangalore Suburban Railway Project in and around Bangalore City10553625RITES  LIMITED, Bangalore
4K RIDE/Projects/59/202002.10.202022.01.2021Package 1: Consultancy Services for Land Parcels and Stations Development for Bengaluru Sub-urban Rail corridors 2 & 454398000IDECK, Bnaglore
5KRIDE/Projects/55/DBH/202026.08.202026.11.2020Baiyyappanahalli – Hosur Doubling Project :Baiyyappanahalli – Hosur Doubling Project 08-02-2022 – E/w. in cutting ,embankment  HEELALIGE & ANEKAL Road Station Yard78260504M/s. Bava Infrastructure Developer Pvt Ltd
Mangalore
6KRIDE/Projects/61/ 202006.11.202018.01.2021Package- 2 –   “Baiyyappanahalli – Hosur  Doubling  project : Collection and supply of machine crushed stone ballast on cess from Km.157/600 to 182/40070585320M/s. R K Construction
Tamil Nadu
7KRIDE/Projects/63/202011.11.202007.10.2021Plate Screws, Clamps for joggled fish plates, CI Bracket, CI distant blocks and M.S Packing piece.2037388M/s. Ganpati Industrial Pvt Ltd, Kolkata
8KRIDE/Projects/53/DYC/1/202030.07.202016.12.2020 Yeshwanthapur – Channasandra  doubling project :Earthwork in cutting, embankment and construction of Minor bridges and other miscellaneous workskm 214/500 to Km 224/700 (Reach –  2)216660021M/s. RMNL – BIDPL (JV),
Hyderabad
9KRIDE/Projects/54/VEH/1/202005.08.202019.11.2020Providing Vehicles with skilled Drivers24,30,00,00Nagesh Travals, Bangalore
10KRIDE/Projects/55/DBH/202026.08.202023.12.2020Baiyyappanahalli – Hosur Doubling Project :Earthwork in cutting, embankment and construction of Minor bridges and other miscellaneous worksBYPL-HSRA E/w.in cutting, embankment in BELENDUR Stn.162311081M/s. Bava Infrastructure Developer Pvt Ltd
Mangalore
11KRIDE/Projects/67/202017.12.2020.03.02.2021Baiyyappanahalli – Hosur Doubling Project : Providing of additional vent way for the exg. ROB No.420 at Km.163/100-200 by RCC Box “Cut & Cover Method” between Anekal Road and Hosur Stations66503293Balaji Enterprises,
Bangalore
12KRIDE/Projects/57/DBH/3/202010.09.202014.12.2020Baiyyappanahalli – Hosur Doubling Project  -Pakage 1-Linking Track km 205/500-182/300102406559M/s. B M Construction
Tamil Nadu
13K RIDE/Projects/58/202016.09.202025.11.2020Providing professional house keeping services along with waste disposal, security services etc.3522560Munisawamy  Nagendra, Bangalore
14KRIDE/Projects/52/DBH/1/202029.07.202017.12.2020Baiyyappanahalli – Hosur Doubling Project: Earthwork in cutting, embankment and construction of Minor bridges and other miscellaneous worksKm 165/500 to Km 174/590 (Reach- 4)213519111M/s. RMNL – BIDPL (JV),
Hyderabad
15K RIDE/Projects/59/202002.10.202024.02.2021Package 2: Consultancy Services for Land and Stations Development for Bengaluru Sub-urban Rail corridors 1 & 399700000THE BOSTON CONSULTING GROUP (INDIA) PVT LTD
16KRIDE/Projects/60/202028.10.202023.04.2021Glass Filled  Nylon -66 Insulated Liners.1565620 M/s. Sheth & Co, Mumbai-400058
17KRIDE/Projects/60/202028.10.202010.11.2021 Glued Insulated Rail Joints 60 Kg & 52 Kg rails.1672664M/s. Kontinental Steel Korporation
Kolkata
18KRIDE/Projects/38/US/202020.02.202018.05.2020Survey, Identification & Investigation of underground, over-ground & overhead Utilities & Structures using Ground Penetrating Radar [GPR) System & Manual Trenching and preparation of Conceptual Diversion Plans & Estimates for shifting the Utilities & Structures in connection with the work of Bangalore Suburban Railway Project in and around Bangalore City16430969RITES  LIMITED, Bangalore
19KRIDE/Projects/60/202028.10.202009.04.2021  Grooved Rubber Sole Plates for 60 Kg PSC Line Sleepers and Points & Crossings Sleepers.2126713M/s. D.K.Steels
Kolkata
20KRIDE/Projects/52/DBH/1/202029.07.202016.12.2020Baiyyappanahalli – Hosur Doubling Project:Earthwork in cutting, embankment and construction of Minor bridges and other miscellaneous worksKm 174/590 to Km 182/500 (Reach – 3)229161185M/s. RMNL – BIDPL (JV),
Hyderabad
21KRIDE/Projects/60/202028.10.202022.06.2021 Joggled Fish Plates with C clamps for 60Kg & 52 kg rails.2201172M/s Techma Engineering Enterprise Pvt Ltd
Kolkata
22KRIDE/Projects/60/202028.10.202019.03.2021 Metal Liners for 60 Kg & 52 Kg rails.6753710M/s.  Royal Infraconstru Limited
Kolkata
23KRIDE/Projects/60/202028.10.202012.04.2021 Metal Liners for 60 Kg & 52 Kg rails.16845720M/s. Shree Laxmi Iron & Steel Works Pvt Ltd
Kolkata
24KRIDE/Projects/60/202028.10.202002.06.2021 Thick web switches – 1 in12 , over riding curved switches – 1 in 8.5 & Derailing switches 60 Kg .45419380M/s. VOSSLOH COGIFER TURNOUTS INDIA PVT Medak District
25KRIDE/Projects/60/202028.10.202002.06.2021Thick Web Switches20886000M/s. R.V. Rail Products Pvt. Ltd
Kolkata
26KRIDE/Projects/53/DYC/1/202030.07.202016.12.2020 Yeshwanthapur – Channasandra  doubling project :Earthwork in cutting, embankment and construction of Minor bridges and other miscellaneous worksKm 205/500 to Km 214/500 (Reach- 1)202640416M/s. RMNL – BIDPL (JV),
Hyderabad
27K RIDE/Projects/61/202006.11.202030.06.2021Yesvantpur – Channasandra and Baiyyappanahalli – Hosur and Doubling projectFabrication and Assembling of 52/60kg in situ Glued Joint6705000M/S Eden Vinimay Kolkota
28KRIDE/Projects/62/ 202007.11.202027.12.2020Baiyyappanahalli – Hosur Doubling Project : Linking of BG track between Km.182/300 and Km.157/500 including Anekal Road, Maranayakanahalli & Hosur   yards119257636M/s. B M Construction
Tamil Nadu -631001
29KRIDE/Projects/63/202011.11.202029.04.2021PSC Mono block wide based Sleepers 60Kg.105776050M/s. Rayalaseema Concrete Sleepers Pvt Ltd
Gulbarga
30KRIDE/Projects/63/202011.11.202029.04.2021PSC Mono block wide based Sleepers 60Kg.49234320M/s. Mahadev Prestressed Products Pvt Ltd
Gulbarga
31KRIDE/Projects/63/202011.11.202029.04.2021PSC Mono block wide based Sleepers 60Kg.130419122M/s. Malu Sleepers Pvt Ltd, Bangalore
32KRIDE/Projects/63/202011.11.202006.07.2021PSC Sleepers 60Kg for Points & Crossings 1in12 and 1in8 ½.25277960M/s. Mahadev Prestressed Products Pvt Ltd, Kalaburagi
33KRIDE/Projects/63/202011.11.202018.08.2021PSC Sleepers 60Kg for Points & Crossings 1in12 and 1in8 ½.22427080M/s.Swarnaa Techno Constructions Pvt Ltd, Hubli
34KRIDE/Projects/63/202011.11.202008.07.2021Fish Bolts & nuts and Spherical plain washer.743400M/s.  Ganpati Industrial Pvt Ltd , Kolkata
35KRIDE/Projects/63/202011.11.202011.06.2021Fish Bolts & nuts and Spherical plain washer.36108000M/s. Techma Engineering Enterprise Pvt Ltd, Kolkata
36KRIDE/Projects/58/202016.09.202014.12.2020Yeshwanthapur – Channasandra  doubling Project – Linking of BG track between Yesvantpur and Baiyyappanahalli “A” panel including Yesvantpur, Lottegollahalli, Hebbal and Banaswadi Yards and other misc works,110853582M/s. B M Construction
Tamil Nadu
37KRIDE/Projects/63/202011.11.202026.10.2021Plate Screws, Clamps for joggled fish plates, CI Bracket, CI distant blocks and M.S Packing piece182900M/s Techma Engineering Enterprise Pvt Ltd, Kolkata
38K RIDE/Projects/65/202003.12.202002.02.2021Package 1 : Geotechnical investigation and associated works for Bengaluru Suburban Rail Project – Corridors 2 & 49279198MPACK (MYRTLE Project & consultency pvt ltd )
39K RIDE/Projects/65/202003.12.202018.02.2021Package 2 : Geotechnical investigation and associated works for Bengaluru Suburban Rail Project – Corridors 1 & 310928201Niketan Consultants
40K RIDE/Projects/65/202003.12.202018.02.2021Strucural design for Bangaore suburban railway26035000RITES  LIMITED, Bangaore
41KRIDE/Projects/52/DBH/1/202029.07.202005.01.2021Baiyyappanahalli – Hosur Doubling Projec:t Earthwork in cutting, embankment and construction of Minor bridges and other miscellaneous worksKm 158/700 to km 165/000 (Reach – 5)365073117M/s. RMNL – BIDPL (JV),
Hyderabad
42KRIDE/Projects/66/202009.12.202002.02.2020Yeshwanthapur – Channasandra  doubling project : – Earthwork in cutting, embankment and construction of Minor bridges and other miscellaneous works in Hebbal and Banaswadi Station yardsn79022063M/s. Bava Infrastructure Developer Pvt Ltd
Mangalore
43KRIDE/DL/01/202114.01.202114.06.2021Signaling outdoor works at Baiyyappanahalli-A panel and Belandur Road in connection  with doubling of BYPL-HSRA section of Bangalore Division.(Package-1)138621321  M/s. Ganapathy Engg. works , Hubli
44KRIDE/DL/01/202114.01.202114.06.2021Signaling outdoor works at Heelalige and Anekal Road  in connection  with doubling of BYPL-HSRA section of Bangalore Division. (Package-2)152469674 M/s. Progressive Engg. Mysore
45KRIDE/DL/02/202121.01.202111.06.2021Signaling works at 2- IBS and 11 LC Gates in connection   with doubling of BYPL-HSRA section of Bangalore Division.150305032 M/s. Vineela Enterprises. Secunderabad
46KRIDE/DL/02/202121.01.202123.06.2021Signaling outdoor works at Hebbal  and Banasawadi in connection  with doubling of  YPR-CSDR section of Bangalore Division.143832448 M/s. G.Satish Ent. Secunderabad
47KRIDE/DL/03/202122.01.202111.06.2021Signaling outdoor works  and indoor alterations to existing EI at Maranayakanahalli (Ansaldo make EI) and Hosur ( Kyosan) in connection  with doubling of BYPL-HSRA section of Bangalore Division. (Single Package)126693710 M/s. Progressive Engg. Mysore
48KRIDE/DL/03/202122.01.202111.06.2021Signaling outdoor works and indoor aletrations to existing EI at  YPR Bye-pass( Ansaldo make EI)and out door signalling work at Lottegollahalli  in connection  with doubling with Auto signalling in YPR-CSDR section of Bangalore Division.110954295 M/s. Vineela Enterprises. Secunderabad
49KRIDE/DL/04/202130.01.202114.06.2021CMS Crossing24874400M/s. Voestalpine VAE VKN India Pvt Ltd
Delhi
50KRIDE/DL/05/202102.02.202111.06.2021Signaling works at one  IBS and 7 (seven) LC Gates in connection   with doubling of YPR-C section of Bangalore Division.75531893 M/s Ganapathi engg company (Anjeneyalu)
51 KRIDE/DL/08/202125.02.202122.06.2021Baiyyappanahalli – Hosur Doubling Project :Proposed  construction of Station Building, Platforms, FOB’s and Platform Shelters at Heelalige & Anekal Road Railway Stations including all Electrical works and other miscellaneous works154013048M/s. SRICO Projects Pvt Ltd ,
Hyderbad
52KRIDE/DL/09/202126.02.202125.06.2021Signalling indoor work with  Electronic intelocking at Baiyappanahalli-A panel, Belandur Road, Heelalige and Anekal Road  in connection with doubling of BYPL-HSRA section of Bangalore Division.118493892  M/s SS Railworks Ltd, Hyderabad
53KRIDE/DL/10/202127.02.202125.05.2021Signalling indoor work with  Electronic intelocking at Lottegollahalli,  Hebbal and Banasawadi  in connection  with doubling of YPR-CSDR  section of Bangalore Division.101321550M/s. G.Satish Enterprises Secunderabad)
54KRIDE/DL/14/202126.03.202111.06.2021Shifting of Signalling & Telecommunication cables, Location boxes and signals in Heelalige  to Hosur section to facilitate civil engineering earth work in connection with doubling of BYPL-HSRA section of Bangalore Division.4535534M/s. INDUSTRUS INC. JAIPUR
55K-RIDE/DL/12/202111.03.202111.06.2021Baiyyappanahalli – Hosur Doubling Project – “Collection and supply of Machine crushed stone Ballast on Cess from Km.182/400 to Km.205/300 in Heelalige (Incl) – Baiyyappanahalli ‘A’ panel section and also depot collection at KM 188/200 (Huskur village)87034038M/s. R K Construction  Tamil Nadu
56K-RIDE/DL/05/2021/505705.04.202105.04.2021Providing skilled manpower to K-RIDE for office/field work”19677436Ms Digital Web world Private Limited ,Delhi